Upcoming OBW Construction
Week of October 22, 2018

 

Brothers Market on Broadway

  • Iron workers will continue decking and installing steel for the future grocery store into November.
  • A large crane will be set up on Broadway to unload and erect steel for the upper floors starting on Friday, October 19th.  A police detail will be in place.

Lobby and Elevator

  •  Elevator 4 continues to be out of service for modernization and inspection.

Building Construction Site (former Surface Parking Lot)

  • Drilling will continue in the core section for the new building foundation at 165 Main Street.  The surface mini piles are in place.
  • Emergency egress from Stair 3 is through the garage, where the garage doors will automatically open in the event of an emergency.  Please follow signage.

Third and Broad Canal streets

  • New curb and sidewalk work will take place at the corner of Broad Canal and Third during the week of October 22nd.
  • Crews continue to relocate a gas line on the northern side of the building near Broad Canal Street.
  • Installation and tie-in of a sewer manhole will take place this week.

Roof and Stairwell Work

  • Removal of fireproofing, relocation of MEP’s (mechanical, electrical, and plumbing), and additional demolition for beam access in BookBub will continue into early next week.
  • Steel installation for the next week will take place mid-to-late next week.

Basement Work

  • Installation of stair wall near Brothers loading dock area will be underway the week of October 22nd.
  • Framing and shoring is underway.
  • Plumbing, HVAC and electrical work are ongoing.
  • Elevator shaft work for Brothers will take place this week.
  • Cutting of the first floor slab for Brothers shaft will take place this week.

Retail Space on First Floor Corner of Third Street and Broadway

  • The new retail tenant will be taking over the space this fall.

Thank you for your continued cooperation and patience!