Upcoming OBW Construction
Week of December 10, 2018

 

Brothers Market on Broadway, Annex Roof, Terrace and Stairwell Work

  • A temporary wall will be installed on the 5th floor on Saturday, December 8th.
  • Iron workers will continue decking and installing steel on the terrace and top floors the week of December 10th.
  • Rebar and mesh will be installed on terrace.
  • Concrete will be placed at Level 3.
  • Work will continue at Stairwell 3 during the week of December 10th.
  • Spray on fireproofing will take place on Levels 1 and 2.
  • Exterior framing and slab placement for Phase III of the lobby will be take place.

Lobby and Elevator

  • Lobby stair installation will take place outside behind the temporary wall.
  • Elevator 4 continues to be out of service for modernization, and the inspection is scheduled for December 14th.

Building Construction Site (former Surface Parking Lot)

  • Emergency egress from Stair 3 is through the garage, where the garage doors will automatically open in the event of an emergency.  Please follow signage.

Liner Retail Building at Broad Canal Street

  • Mini pile drilling will continue to take place through the week of December 10th.

Basement Work

  • Elevator shaft opening will be cut to Level 1.
  • Bathroom walls and plumbing will be installed the week of December 10th.
  • Framing and shoring is underway.
  • Plumbing, HVAC and electrical work are ongoing.

Retail Space on First Floor Corner of Third Street and Broadway

  • The new retail tenant will begin outfitting their space later this fall.

Thank you for your continued cooperation and patience!