Upcoming OBW Construction

Week of June 17, 2019

Addition Work *

  • Cutting of column gussets and weld supports at the terrace will continue to take place. Expect L1 and occasional L2 noise at the terrace window area on 5th floor annex.
  • Preparation for the placement of the topping slab on the east side terrace will continue, followed by placement and finishing work. Expect L1 noise on the 5th floor annex.
  • Decking will be installed at the mechanical doghouse at the annex roof on Friday, June 14th and Saturday, June 15th.
  • Framing will begin at the mechanical doghouse next week. Expect L1 to L2 noise in 5th floor annex.
  • Trim installation for the eastern tower 3rd/4th will continue.
  • Crews will do finish work at the terrace entrance area on the 5th floor annex.
  • The headhouse Stairwell 3 interior work will continue with installation of fire alarm wiring and the sprinkler system, as well as exterior panel work.
  • RTU power will be run inside the mechanical shaft to the annex roof. Expect L1 noise in 5th floor annex.
  • Re-configuring of the ducts on the annex roof will continue on Friday, June 14th and Saturday, June 15th and finish up next week. Expect L1 noise in 5th floor annex.
  • Demolition of the metal panel canopy on the terrace will take place at least in the early mornings. Expect L1 and L2 noise in the 5th floor annex.

Lobby and Elevator

  • Miscellaneous finish work will continue.
  • Office elevator installation continues to the 2nd floor new offices.

165 Main Street Construction Site (former Surface Parking Lot)

  • Emergency egress from Stair 3 is through the garage, where the garage doors will automatically open in the event of an emergency. Please follow signage.
  • Concrete continues to be prepped and placed in the receiving area of the loading dock
  • Overhead MEP’s (mechanical, electrical, and plumbing) will continue to be installed.
  • CMU wall installation is ongoing.
  • Plumbing installation will occur.

Liner Retail Building at Broad Canal Street

  • Wood rain screen work continues.
  • Site lighting will be installed.
  • Electrical work will occur.
  • Interior framing will take place.
  • Hardscaping work continues.

Basement and Sidewalk on Third Street

  • Miscellaneous work and outfitting work for the market and restaurant is underway.

Brothers Market

  • Brothers Market outfitting is underway.
  • Blocking for scrubber will occur. Expect L1 and possible L2 noise on the 5th floor annex.

Shy Bird Restaurant on First Floor Corner of Third Street and Broadway

  • Shy Bird continues to outfit their space.

* Please note, much of the roof and terrace work will be performed weather permitting. 

Thank you for your continued cooperation and patience!